Punch List
Washington St | 2026-05-10
PL-3
MDC Development
Josh Marcotte
joshmarcotte@gmail.com
978 728 8789

Complete Washington St.

Send status: NotSent  |  List state: Open

Customer approved: No  |  Approved date: —

DescriptionStatusCompletedNotesPic
HVAC InstallationOpen—Start May 11, Target Complete May29—
InsullationOpen—Start June 15th, Target Complete June 19th—
Ruff WiringOpen———
Finish WiringOpen———
Gas Pipe for HeaterOpen—Schedule with Plumber with HVAC—
Schedule InspectionOpen—Call Week of June 22—
Interior DoorsOpen—After Sheetrock—
Exterior DoorsOpen—Order Doors, install by 6/8—
SheetrockOpen—Start Week of June 22—
Trim / BaseboardOpen—Start wee of 7/7—
Deck (first and second floorr)Open—Start 5/25—
Cellar FramingOpen—Start 5/27—
Misc FramingOpen—As needed—
LandscapingOpen—End of July—