Punch List
Washington St | 2026-05-10
PL-3
MDC Development
Josh Marcotte
joshmarcotte@gmail.com
978 728 8789

Complete Washington St.

Send status: NotSent  |  List state: Open

Customer approved: No  |  Approved date:

DescriptionStatusCompletedNotesPic
HVAC InstallationOpenStart May 11, Target Complete May29
InsullationOpenStart June 15th, Target Complete June 19th
Ruff WiringOpen
Finish WiringOpen
Gas Pipe for HeaterOpenSchedule with Plumber with HVAC
Schedule InspectionOpenCall Week of June 22
Interior DoorsOpenAfter Sheetrock
Exterior DoorsOpenOrder Doors, install by 6/8
SheetrockOpenStart Week of June 22
Trim / BaseboardOpenStart wee of 7/7
Deck (first and second floorr)OpenStart 5/25
Cellar FramingOpenStart 5/27
Misc FramingOpenAs needed
LandscapingOpenEnd of July